EXERCISE
As the operations manager, assign trucks to delivery routes so that total costs are minimized,
given the cost data shown. What is the total cost? The cost for each route is in N000.
Truck
Route
A
B
C
D
E
1
4
5
9
8
7
2
6
4
8
3
5
3
7
3
10
4
6
4
5
2
5
5
8
5
6
5
3
4
9
give step by step answer with explanation and conclution
Question:
EXERCISE
As the operations manager, assign trucks to delivery routes so that total costs are minimized,
given the cost data shown. What is the total cost? The cost for each route is in N000.
Truck
Route
A
B
C
D
E
1
4
5
9
8
7
2
6
4
8
3
5
3
7
3
10
4
6
4
5
2
5
5
8
5
6
5
3
4
9
give step by step answer with explanation and conclution
This is AI generated Response.
Asked by: Test User 100107
Created at: 2025-04-29 09:29:59
Final Answer:
RenderedRaw Text
Did you like this answer?
Let's solve the **assignment problem** where 5 trucks (A, B, C, D, E) need to be assigned to 5 routes (1, 2, 3, 4, 5) such that the total cost is minimized. We will use the **Hungarian Method** (also called the Assignment Method) step by step.
---
### Step 1: Write the Cost Matrix
| | 1 | 2 | 3 | 4 | 5 |
|------|---|---|---|---|---|
| **A**| 4 | 6 | 7 | 5 | 8 |
| **B**| 5 | 4 | 3 | 2 | 5 |
| **C**| 9 | 8 |10 | 5 | 6 |
| **D**| 8 | 3 | 4 | 6 | 5 |
| **E**| 7 | 5 | 6 | 5 | 9 |
---
### Step 2: Row Reduction
Subtract the smallest value in each row from all elements in that row.
- Row A min = 4; subtract 4 from row A
- Row B min = 2; subtract 2 from row B
- Row C min = 5; subtract 5 from row C
- Row D min = 3; subtract 3 from row D
- Row E min = 5; subtract 5 from row E
| | 1 | 2 | 3 | 4 | 5 |
|------|---|---|---|---|---|
| **A**| 0 | 2 | 3 | 1 | 4 |
| **B**| 3 | 2 | 1 | 0 | 3 |
| **C**| 4 | 3 | 5 | 0 | 1 |
| **D**| 5 | 0 | 1 | 3 | 2 |
| **E**| 2 | 0 | 1 | 0 | 4 |
---
### Step 3: Column Reduction
Find the minimum value in each column and subtract it from the column.
- Col 1 min = 0; subtract 0 from column 1
- Col 2 min = 0; subtract 0 from column 2
- Col 3 min = 1; subtract 1 from column 3
- Col 4 min = 0; subtract 0 from column 4
- Col 5 min = 1; subtract 1 from column 5
| | 1 | 2 | 3 | 4 | 5 |
|------|---|---|---|---|---|
| **A**| 0 | 2 | 2 | 1 | 3 |
| **B**| 3 | 2 | 0 | 0 | 2 |
| **C**| 4 | 3 | 4 | 0 | 0 |
| **D**| 5 | 0 | 0 | 3 | 1 |
| **E**| 2 | 0 | 0 | 0 | 3 |
---
### Step 4: Assign Zeros (Hungarian Method)
We need to cover all zeros with a minimum number of lines and check if we can make assignments.
#### **First, mark independent zeros (no row/col has more than one assigned zero):**
- **Row A:** 1 zero (col 1)
- **Row B:** 2 zeros (col 3, 4)
- **Row C:** 2 zeros (col 4, 5)
- **Row D:** 2 zeros (col 2, 3)
- **Row E:** 3 zeros (col 2, 3, 4)
Let's proceed to assign zeros:
1. **Row A** has only one zero (col 1). Assign A-1.
2. **Row D** now has only one remaining zero (col 2). Assign D-2.
3. **Row B** now has only one zero left (col 3). Assign B-3.
4. **Row C** now has two zeros (col 4, 5). Let's pick col 5 for C (arbitrary, will check if better assignment possible later).
5. **Row E** now has one zero left (col 4). Assign E-4.
Let's see if this is a valid assignment:
- **A-1**
- **D-2**
- **B-3**
- **E-4**
- **C-5**
Check if any two assignments are in the same column: all are unique, so this is a valid assignment.
---
### Step 5: Calculate the Total Cost
Now substitute back to the **original cost matrix**:
- **A-1:** 4
- **D-2:** 3
- **B-3:** 3
- **E-4:** 5
- **C-5:** 6
**Total cost = 4 + 3 + 3 + 5 + 6 = 21 (in N000) = N21,000**
---
### Step 6: Conclusion
**Assignments:**
- Truck A → Route 1
- Truck B → Route 3
- Truck C → Route 5
- Truck D → Route 2
- Truck E → Route 4
**Minimum Total Cost:** **N21,000**
---
#### **Summary Table**
| Truck | Route | Cost (N000) |
|-------|-------|-------------|
| A | 1 | 4 |
| B | 3 | 3 |
| C | 5 | 6 |
| D | 2 | 3 |
| E | 4 | 5 |
|**Total**| | **21** |
---
**Therefore, the minimum total cost is N21,000, and the assignments are as above.**
Question:
ones more
This is AI generated Response.
Asked by: Test User 100107
Created at: 2025-04-29 09:31:27
Final Answer:
RenderedRaw Text
Did you like this answer?
Let's carefully solve the assignment problem to minimize total costs for assigning trucks to routes.
---
### Given Data:
| Truck | Route 1 | Route 2 | Route 3 | Route 4 | Route 5 |
|--------|---------|---------|---------|---------|---------|
| **A** | 4 | 6 | 7 | 5 | 8 |
| **B** | 5 | 4 | 3 | 2 | 5 |
| **C** | 9 | 8 | 10 | 5 | 6 |
| **D** | 8 | 3 | 4 | 6 | 5 |
| **E** | 7 | 5 | 6 | 5 | 9 |
---
### Step 1: Row Reduction
Subtract the minimum value in each row from all entries in that row:
- Row A min = 4 → subtract 4:
- A: 0, 2, 3, 1, 4
- Row B min = 2 → subtract 2:
- B: 3, 2, 1, 0, 3
- Row C min = 5 → subtract 5:
- C: 4, 3, 5, 0, 1
- Row D min = 3 → subtract 3:
- D: 5, 0, 1, 3, 2
- Row E min = 5 → subtract 5:
- E: 2, 0, 1, 0, 4
**Updated matrix:**
| | 1 | 2 | 3 | 4 | 5 |
|------|---|---|---|---|---|
| **A**| 0 | 2 | 3 | 1 | 4 |
| **B**| 3 | 2 | 1 | 0 | 3 |
| **C**| 4 | 3 | 5 | 0 | 1 |
| **D**| 5 | 0 | 1 | 3 | 2 |
| **E**| 2 | 0 | 1 | 0 | 4 |
---
### Step 2: Column Reduction
Subtract the minimum value in each column from all entries in that column:
- Column 1 min = 0 → no change
- Column 2 min = 0 → no change
- Column 3 min = 1 → subtract 1:
- C: 4→3, D: 1→0, others unchanged
- Column 4 min = 0 → no change
- Column 5 min = 1 → subtract 1:
- A: 4→3, others unchanged
**Updated matrix after column reduction:**
| | 1 | 2 | 3 | 4 | 5 |
|------|---|---|---|---|---|
| **A**| 0 | 2 | 3 | 1 | 3 |
| **B**| 3 | 2 | 1 | 0 | 2 |
| **C**| 4 | 3 | 3 | 0 | 0 |
| **D**| 5 | 0 | 0 | 3 | 1 |
| **E**| 2 | 0 | 0 | 0 | 3 |
---
### Step 3: Cover Zeros
Identify the minimum number of lines needed to cover all zeros:
Zeros are at positions:
- A: col 1
- B: col 4
- C: cols 4, 5
- D: cols 2, 3
- E: cols 2, 3, 4
Possible assignment:
- Assign A to Route 1 (zero at A-1)
- Assign D to Route 2 (zero at D-2)
- Assign B to Route 4 (zero at B-4)
- Assign C to Route 5 (zero at C-5)
- Assign E to Route 3 (zero at E-3)
Check if all zeros are covered with 5 lines: yes, since each zero is in a unique row/column combination.
---
### Step 4: Final Assignments and Cost Calculation
Now, map these assignments back to the original costs:
| Truck | Route | Original Cost |
|--------|--------|---------------|
| A | 1 | 4 |
| D | 2 | 3 |
| B | 4 |
VIPSolutions focuses on clear, step‑by‑step explanations so you can learn quickly. Whether you need an AI‑generated walkthrough or a short hint to get unstuck, each solution is organized for fast reading and easy review later.
Search similar questions, compare approaches, and bookmark the best answers for revision. Our goal is simple: quick, reliable study help that feels natural—not noisy.