Following the exercise below, the switch to go
-
away costs for determining savings sharply reduced the projected savings for two of the three services and showed that contracting custodial services would actually increase costs. Critical to this change is how much overhead would actually be reduced for the go
-
away options compared to the full cost estimates. The manager is concerned that many of these overhead costs would not actually disappear or go
-
away.
If Buckaroo decides that it will only make a shift to contractors if savings are equal to at least
1
0
percent of the go away costs, how much of the overhead costs under a full cost calculation would need to actually go away to justify the switch? Please show the work.
give full answer and give final summaryGo-Away Costs Compared to Contract Costs for Buckaroo Wyoming
[ inHowe |]
Savings via Savings via
Contractivi Contractil
ETE —— Compared os 0
Full Costs Away Costs
Custodial Services
Salaries/wages $90,854 $90,854
Fringe benefits $20,798 $20,798
Other operating costs $24,125 $24,125
Overhead” $22,814 $4,200
Low bid $142,000
Contract administration” $5,000
Total $158,591 $139,977 $147,000 $11,501 $7,023
I A A A
Fleet Maintenance
Salaries/wages $136,914 $136,914
Fringe benefits $30,216 $30,216
Other operating costs $34,031 $34,031
Overhead” $35,121 $16,542
Low bid $156,500
Contract administration” $11,000
Total $236,282 $217,703 $167,500 $68,782
rr rr]
Residential Refuse Collection
Salaries/wages $230,851 $230,851
Fringe benefits $56,851 $56,851
Other operating costs $901,852 $901,852
Overhead” $203,543 $95,054
Low bid $1,244,000
Contract administration” $14,000
Total $1,393,097 $1,284,608 $1,258,000 $135,097 $26,608
ToTAL
Question:
Following the exercise below, the switch to go
-
away costs for determining savings sharply reduced the projected savings for two of the three services and showed that contracting custodial services would actually increase costs. Critical to this change is how much overhead would actually be reduced for the go
-
away options compared to the full cost estimates. The manager is concerned that many of these overhead costs would not actually disappear or go
-
away.
If Buckaroo decides that it will only make a shift to contractors if savings are equal to at least
1
0
percent of the go away costs, how much of the overhead costs under a full cost calculation would need to actually go away to justify the switch? Please show the work.
give full answer and give final summaryGo-Away Costs Compared to Contract Costs for Buckaroo Wyoming
[ inHowe |]
Savings via Savings via
Contractivi Contractil
ETE —— Compared os 0
Full Costs Away Costs
Custodial Services
Salaries/wages $90,854 $90,854
Fringe benefits $20,798 $20,798
Other operating costs $24,125 $24,125
Overhead” $22,814 $4,200
Low bid $142,000
Contract administration” $5,000
Total $158,591 $139,977 $147,000 $11,501 $7,023
I A A A
Fleet Maintenance
Salaries/wages $136,914 $136,914
Fringe benefits $30,216 $30,216
Other operating costs $34,031 $34,031
Overhead” $35,121 $16,542
Low bid $156,500
Contract administration” $11,000
Total $236,282 $217,703 $167,500 $68,782
rr rr]
Residential Refuse Collection
Salaries/wages $230,851 $230,851
Fringe benefits $56,851 $56,851
Other operating costs $901,852 $901,852
Overhead” $203,543 $95,054
Low bid $1,244,000
Contract administration” $14,000
Total $1,393,097 $1,284,608 $1,258,000 $135,097 $26,608
ToTAL
This is AI generated Response.
Asked by: sreegeeth
Created at: 2025-10-28 19:02:27
Final Answer:
RenderedRaw Text
Did you like this answer?
# Overhead Cost Reduction Needed to Just Contractor Switch
## **Problem Restatement**
Buckaroo will only switch to contractors if the **savings are at least 10% of the go-away costs**. The key question is:
**How much of the overhead costs under the full cost calculation would need to actually go away to meet this threshold?**
We'll solve this step-by-step.
---
## **Step 1: Calculate 10% Savings Threshold**
**Go-away costs (total):**
From the table:
\[
\text{Go-Away Costs (Total)} = \$1,284,608
\]
**Required minimum savings:**
\[
10\% \times \$1,284,608 = \$128,461
\]
---
## **Step 2: Calculate Current Projected Savings (Compared to Go-Away Costs)**
From the table, **total savings via contracting compared to go-away costs**:
\[
\text{Current Projected Savings} = \$69,788
\]
---
## **Step 3: Determine Additional Savings Needed**
\[
\text{Additional Savings Needed} = \text{Required Savings} - \text{Current Projected Savings}
\]
\[
= \$128,461 - \$69,788 = \$58,673
\]
---
## **Step 4: Overhead in Go-Away Costs**
### Overhead in Full Cost vs. Go-Away Cost
| Service | Overhead (Full Cost) | Overhead (Go-Away) | Difference |
|--------------------------|---------------------|--------------------|------------|
| Custodial Services | $22,814 | $4,200 | $18,614 |
| Fleet Maintenance | $35,121 | $16,542 | $18,579 |
| Residential Refuse Coll. | $203,543 | $95,054 | $108,489 |
| **TOTAL** | **$261,478** | **$115,796** | **$145,682**|
So, currently, of the **$261,478** full cost overhead, **$145,682** is already being "taken away" in the go-away cost scenario.
---
## **Step 5: How Much More Overhead Needs to Go Away?**
We need to close the gap of **$58,673** in additional savings.
If we reduce go-away overhead by $58,673 more, the savings target will be met.
### **Current go-away overhead: $115,796**
\[
\text{Overhead that must actually go away} = \$115,796 - \$58,673 = \$57,123
\]
So, only **$57,123** of the original overhead would remain.
Alternatively, **$261,478 - $57,123 = $204,355** of the full cost overhead would need to "go away" (be eliminated).
---
## **Step 6: Express as a Percentage**
\[
\frac{\$204,355}{\$261,478} \approx 78.2\%
\]
So, **at least 78.2% of the full cost overhead** would need to actually go away for the contractor switch to achieve the 10% savings threshold.
---
# **Final Summary**
**To justify switching to contractors (with savings of at least 10% of go-away costs), Buckaroo would need at least $204,355 of the $261,478 in overhead costs (78.2%) to truly go away.** If less than this amount of overhead is eliminated, the savings target will not be met, and the switch would not be justified.
**Key calculation:**
- **Required savings:** $128,461
- **Current projected savings:** $69,788
- **Additional overhead to eliminate:** $58,673
- **Total overhead to "go away":** $204,355 (78.2% of original overhead)
Question:
give correct table
This is AI generated Response.
Asked by: sreegeeth
Created at: 2025-10-28 19:05:25
Final Answer:
RenderedRaw Text
Did you like this answer?
# Overhead Cost Reduction Needed to Justify Contractor Switch
## Problem Restatement
Buckaroo will only switch to contractors if the **savings are at least 10% of the go-away costs**. We need to determine how much overhead costs under the full cost calculation must actually be reduced to justify this switch.
---
## Step 1: Calculate 10% Savings Threshold
**Go-away costs (total):**
\[
\text{Go-Away Costs (Total)} = \$1,284,608
\]
**Required minimum savings:**
\[
10\% \times \$1,284,608 = \$128,461
\]
---
## Step 2: Calculate Current Projected Savings
**Total savings via contracting compared to go-away costs:**
\[
\text{Current Projected Savings} = \$69,788
\]
---
## Step 3: Determine Additional Savings Needed
\[
\text{Additional Savings Needed} = \text{Required Savings} - \text{Current Projected Savings}
\]
\[
= \$128,461 - \$69,788 = \$58,673
\]
---
## Step 4: Overhead in Go-Away Costs
### Overhead in Full Cost vs. Go-Away Cost
| Service | Overhead (Full Cost) | Overhead (Go-Away) | Difference |
|--------------------------|---------------------|--------------------|--------------|
| Custodial Services | $22,814 | $4,200 | $18,614 |
| Fleet Maintenance | $35,121 | $16,542 | $18,579 |
| Residential Refuse Coll. | $203,543 | $95,054 | $108,489 |
| **TOTAL** | **$261,478** | **$115,796** | **$145,682** |
The total overhead under full cost is **$261,478**, while the total in go-away costs is **$115,796**. The difference amounts to **$145,682**.
---
## Step 5: How Much More Overhead Needs to Go Away?
To meet the required additional savings of **$58,673**, we need to further reduce overhead costs.
### Calculation of Required Overhead Reduction
\[
\text{Overhead that must actually go away} = \text{Current Go-Away Overhead} - \text{Additional Savings Needed}
\]
\[
= \$115,796 - \$58,673 = \$57,123
\]
Therefore, **$57,123** of overhead would need to remain.
Alternatively, the total overhead that must be removed from the full cost overhead is:
\[
\text{Total Overhead to "Go Away"} = \$261,478 - \$57,123 = \$204,355
\]
---
## Step 6: Express as a Percentage
To find the percentage of the overhead that needs to go away:
\[
\text{Percentage} = \frac{\$204,355}{\$261,478} \approx 78.2\%
\]
---
# Final Summary
To justify switching to contractors (with savings of at least 10% of go-away costs), Buckaroo would need at least **$204,355** of the **$261,478** in overhead costs (approximately **78.2%**) to actually go away. If less than this amount of overhead is eliminated, the savings target will not be achieved, making the switch unjustifiable.
**Key Calculations:**
- **Required savings:** $128,461
- **Current projected savings:** $69,788
- **Additional savings needed:** $58,673
- **Total overhead to "go away":** $204,355 (78.2% of original overhead)
Question:
give 2 sentence summary in each steps
This is AI generated Response.
Asked by: sreegeeth
Created at: 2025-10-28 19:08:01
Final Answer:
RenderedRaw Text
Did you like this answer?
# Summary of Each Step
## Step 1: Calculate 10% Savings Threshold
The total go-away costs amount to **$1,284,608**. To achieve the required savings threshold of **10%**, Buckaroo needs to save at least **$128,461**.
## Step 2: Calculate Current Projected Savings
The current projected savings from switching to contractors compared to the go-away costs is **$69,788**. This figure represents the apparent savings that Buckaroo would realize by contracting services instead of maintaining internal operations.
## Step 3: Determine Additional Savings Needed
To meet the required savings of **$128,461**, Buckaroo must identify an additional **$58,673** in savings. This gap highlights the need for further reductions in overhead costs.
## Step 4: Overhead in Go-Away Costs
The total overhead under full cost is **$261,478**, while the overhead in go-away costs is **$115,796**. The difference of **$145,682** represents the potential reductions available if the go-away options are pursued.
## Step 5: How Much More Overhead Needs to Go Away?
To meet the additional savings requirement of **$58,673**, the overhead that must actually go away is calculated to be **$57,123**. This indicates that a total of **$204,355** of the overhead would need to be eliminated from the full cost for a contractor switch to be justified.
## Step 6: Express as a Percentage
The calculated percentage of overhead that needs to be removed is approximately **78.2%** of the full cost overhead. This percentage illustrates the significant reduction required in overhead to validate the contractor switch.
VIPSolutions focuses on clear, step‑by‑step explanations so you can learn quickly. Whether you need an AI‑generated walkthrough or a short hint to get unstuck, each solution is organized for fast reading and easy review later.
Search similar questions, compare approaches, and bookmark the best answers for revision. Our goal is simple: quick, reliable study help that feels natural—not noisy.