Give step-by-step solution with explanation and final answer:uestion 2 Marks: 45) Using the details from question 1 (table 1), create a project electronic solution using any project management tool of your choice, for example, MS Project, Trello, Jira, etc. For each activity, where possible, add at least THREE (3) sub-activities in your project electronic solution. NOTE: A work breakdown structure is usually the best tool to decompose all activities before creating any project electronic solution. Therefore, create the WBS before this exercise. NOTE: see below Annexure A: Marking Guideline H Learning unit/s covered: 1,2,3,4,5 & 6. Annexure A: Marking Guideline EERE Required of Marks | setup of the project information. . | setthe start date/ Finish date (1); i . set applicable calendar (1). Schedule the project as follow: | Project is adequately scheduled (2) b | Configure the work pattern (calendar). | Adequately created a new calendar (1); | le Working times are adequately set (2); | Non working times are adequately set (2)- List activities to be created. } . Outstandingly added as per WBS in the project (5); . Adequately added as per WBS in the project (4); partially added as per WBS in the project (3); b © inadequately added as per WBS in the project (1:2). Tndent and link the activities. |. Outstandingly indented as per WBS in the project (5); . Adequately indented as per WBS in the project (4); partially indented as per WBS in the project (3); 5 inadequately indented as per WBS in the project (1-2). Determine activity duration. L Outstandingly added as per WBS in the project (9-10); le Adequately added as per WBS in the project (6-8); partially added as per WBS in the project (3-5); fo ET 4 as per WBS in the project (1-2). Determined milestones. Outstandingly indented as per WBS in the project (5); Adequately indented as per WBS in the project (4); Partially indented as per WBS in the project (3); Inadequately indented as per WBS in the project (1-2). Configure activity dependencies. Outstandingly configured in the project (5); Adequately configured in the project (4); Partially configured in the project (3); Fr Inadequately configured in the project (1-2). Overall: Schedule the activities/ predecessors/ Gant chart. Outstandingly scheduled (4); o Adequately scheduled (3); Partially scheduled (2); i inadequately schedule (1). i mm piionT 0 A TOTAL =
Question:
Give step-by-step solution with explanation and final answer:

uestion 2 Marks: 45)
Using the details from question 1 (table 1), create a project electronic solution using any project
management tool of your choice, for example, MS Project, Trello, Jira, etc. For each activity,
where possible, add at least THREE (3) sub-activities in your project electronic solution.
NOTE: A work breakdown structure is usually the best tool to decompose all activities before
creating any project electronic solution. Therefore, create the WBS before this exercise.
NOTE: see below Annexure A: Marking Guideline H
Learning unit/s covered: 1,2,3,4,5 & 6.
Annexure A: Marking Guideline EERE
Required of Marks |
setup of the project information.
. | setthe start date/ Finish date (1); i
. set applicable calendar (1).
Schedule the project as follow: |
Project is adequately scheduled (2) b |
Configure the work pattern (calendar). |
Adequately created a new calendar (1); |
le Working times are adequately set (2); |
Non working times are adequately set (2)-
List activities to be created. }
. Outstandingly added as per WBS in the project (5);
. Adequately added as per WBS in the project (4);
partially added as per WBS in the project (3); b
© inadequately added as per WBS in the project (1:2).
Tndent and link the activities.
|. Outstandingly indented as per WBS in the project (5);
. Adequately indented as per WBS in the project (4);
partially indented as per WBS in the project (3); 5
inadequately indented as per WBS in the project (1-2).
Determine activity duration.
L Outstandingly added as per WBS in the project (9-10);
le Adequately added as per WBS in the project (6-8);
partially added as per WBS in the project (3-5); fo
ET 4 as per WBS in the project (1-2).
Determined milestones.
Outstandingly indented as per WBS in the project (5);
Adequately indented as per WBS in the project (4);
Partially indented as per WBS in the project (3);
Inadequately indented as per WBS in the project (1-2).
Configure activity dependencies.
Outstandingly configured in the project (5);
Adequately configured in the project (4);
Partially configured in the project (3); Fr
Inadequately configured in the project (1-2).
Overall: Schedule the activities/ predecessors/ Gant chart.
Outstandingly scheduled (4);
o Adequately scheduled (3);
Partially scheduled (2); i
inadequately schedule (1).
i mm piionT 0 A
TOTAL =
Asked by: Test User 100175
Created at: 2025-05-16 11:47:07
Final Answer:
📢 Instructions:
- Ask anything relatd to above question only.
- For new Question goto :
VIPSolutions