Give step-by-step solution with explanation and final answer:
The Markbreit Company has the opportunity to invest in one of two mutually exclusive machines that will produce a product that Markbreit will need for the next
2
0
years. Machine X costs $
2
5
million but realizes after
-
tax inflows of $
6
million per year for
1
0
years with each inflow recognized at the end of each year. After
1
0
years, any version of Machine X would have to be replaced with another Machine X
.
Machine Y costs $
5
5
million and realizes after
-
tax inflows of $
8
million per year for
2
0
years with each inflow recognized at the end of each year. Assume that machine prices are expected to rise by
3
%
,
per year, due to inflation. The cost of capital is
1
1
%
.
Which is the
‘
better
’
machine for this project
(
Machine X that will need to be replaced once? Or Machine Y that will last the project
’
s
2
0
-
year life
)
?
By how much would the value of the company increase
(
today
)
if it accepted the
‘
better
’
machine for this
2
0
-
year project rather than if it accepted the
‘
worse
’
machine?
(
9
)
Question:
Give step-by-step solution with explanation and final answer:
The Markbreit Company has the opportunity to invest in one of two mutually exclusive machines that will produce a product that Markbreit will need for the next
2
0
years. Machine X costs $
2
5
million but realizes after
-
tax inflows of $
6
million per year for
1
0
years with each inflow recognized at the end of each year. After
1
0
years, any version of Machine X would have to be replaced with another Machine X
.
Machine Y costs $
5
5
million and realizes after
-
tax inflows of $
8
million per year for
2
0
years with each inflow recognized at the end of each year. Assume that machine prices are expected to rise by
3
%
,
per year, due to inflation. The cost of capital is
1
1
%
.
Which is the
‘
better
’
machine for this project
(
Machine X that will need to be replaced once? Or Machine Y that will last the project
’
s
2
0
-
year life
)
?
By how much would the value of the company increase
(
today
)
if it accepted the
‘
better
’
machine for this
2
0
-
year project rather than if it accepted the
‘
worse
’
machine?
(
9
)
This is AI generated Response.
Asked by: Yelligadala Praneesh
Created at: 2025-06-06 04:44:16
Final Answer:
RenderedRaw Text
Did you like this answer?
Let's solve step-by-step:
**Given:**
- **Machine X:**
- Initial cost = $25 million
- Life = 10 years
- After-tax inflow = $6 million/year (end of each year, for 10 years)
- Needs to be replaced after 10 years (for a 20-year project, need to buy it twice)
- Replacement cost increases by 3% per year due to inflation
- **Machine Y:**
- Initial cost = $55 million
- Life = 20 years
- After-tax inflow = $8 million/year (end of each year, for 20 years)
- **Cost of capital:** 11%
- **Inflation for machine price:** 3% per year (for replacement price only)
---
### **Step 1: Calculate NPV for Machine X (over 20 years)**
#### **A. First Machine X: Years 0-9**
- Cost at time 0 = $25M
- Cash inflows: $6M/year for years 1-10
#### **B. Second Machine X: Years 10-19**
- Cost at year 10 = $25M × (1.03)¹⁰
- Cash inflows: $6M/year for years 11-20
---
#### **A1. PV of first 10 years' inflows with Machine X**
PV = \( \sum_{t=1}^{10} \frac{6}{(1.11)^t} \)
This is a present value of an ordinary annuity:
PV = \( 6 \times \left[\frac{1 - (1+0.11)^{-10}}{0.11}\right] \)
- \( (1 + 0.11)^{-10} = (1.11)^{-10} ≈ 0.3522 \)
- \( 1 - 0.3522 = 0.6478 \)
- \( 0.6478 / 0.11 = 5.889 \)
- PV = \( 6 \times 5.889 = 35.33 \) million
#### **A2. PV of first outflow (cost)**
- At year 0: -$25M
---
#### **B1. Cost of replacing Machine X in year 10**
Replacement cost = $25M × (1.03)¹⁰
Calculate \( (1.03)^{10} \):
- \( (1.03)^{10} = 1.3439 \)
- Replacement cost = $25M × 1.3439 = $33.60M
PV of this outflow at year 0:
PV = \( \frac{33.60}{(1.11)^{10}} \)
- \( (1.11)^{10} ≈ 2.8394 \)
- PV = \( 33.60 / 2.8394 = 11.84 \) million
#### **B2. PV of 2nd 10-years' inflows (years 11-20)**
Find PV at year 10, then discount to present:
PV at year 10: Same formula as above:
- PV10 = \( 6 \times 5.889 = 35.33 \) million
Discount to present:
PV0 = \( \frac{35.33}{(1.11)^{10}} = 35.33 / 2.8394 = 12.45 \) million
---
#### **A3. Total NPV for Machine X**
Sum all:
\[
NPV_X = \text{(PV of 1st 10 years inflows)} - \text{(Initial cost)} + \text{(PV of 2nd 10 years inflows)} - \text{(PV of replacement cost)}
\]
\[
NPV_X = 35.33 - 25 + 12.45 - 11.84 = 10.94 \text{ million}
\]
---
### **Step 2: Calculate NPV for Machine Y (over 20 years)**
- Initial cost = $55M at Year 0
- After-tax inflow = $8M/year for 20 years
PV of inflows:
PV = \( 8 \times \left[\frac{1-(1.11)^{-20}}{0.11}\right] \)
- \( (1.11)^{-20} ≈ 0.1240 \)
- \( 1 - 0.1240 = 0.8760 \)
- \( 0.8760 / 0.11 = 7.964 \)
- PV = \( 8 \times 7.964 = 63.71 \) million
NPV = PV of inflows - PV of cost
NPV_Y = 63.71 - 55 = **8.71 million**
---
### **Step 3: Compare NPVs and Find Value Added**
- NPV of Machine X: **$10.94 million**
- NPV of Machine Y: **$8.71 million**
**Machine X** is the better machine for the project.
**Difference in value to company:**
\[
10.94 - 8.71 = 2.23 \text{ million}
\]
---
## **Final Answers**
### **1. Which is the better machine?**
**Machine X** is the better machine for this 20-year project.
### **2. By how much would the value of the company increase if it accepted the better machine (X) instead of the worse (Y)?**
**By $2.23 million.**
---
## **Summary Table**
| Machine | NPV ($ million) | Better? |
|-----------|-----------------|---------|
| X | 10.94 | Yes |
| Y | 8.71 | No |
**Difference in value if choosing X over Y:** $2.23 million
---
If you need to see the calculations in a table or with more decimal precision, let me know!
VIPSolutions focuses on clear, step‑by‑step explanations so you can learn quickly. Whether you need an AI‑generated walkthrough or a short hint to get unstuck, each solution is organized for fast reading and easy review later.
Search similar questions, compare approaches, and bookmark the best answers for revision. Our goal is simple: quick, reliable study help that feels natural—not noisy.