Give step-by-step solution with explanation and final answer:
The demand for subassembly S is 150 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 2 units of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
Click the icon to view the product structure and the time-phased product structure.
Click the icon to view the on-hand inventory.
Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers).
Item
S
1
2
3
5
6
7
Gross req
On hand
Net req
Order receipt
Order release
Week
4
150
0
150
150
150
Lead Time (weeks)
2
Question:
Give step-by-step solution with explanation and final answer:
The demand for subassembly S is 150 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 2 units of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
Click the icon to view the product structure and the time-phased product structure.
Click the icon to view the on-hand inventory.
Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers).
Item
S
1
2
3
5
6
7
Gross req
On hand
Net req
Order receipt
Order release
Week
4
150
0
150
150
150
Lead Time (weeks)
2
This is AI generated Response.
Asked by: Test User 100021
Created at: 2025-05-03 12:11:37
Final Answer:
RenderedRaw Text
Did you like this answer?
Let's carefully analyze and develop the net material requirements plan step-by-step.
---
### Step 1: Understand the demand and structure
- **Demand for S in week 7:** 150 units
- **Lead time for S:** 2 weeks
- **S requires:** 1 unit of T and 1 unit of U per unit of S
- **Lead times:**
- T: 1 week
- U: 2 weeks
- **Subcomponents:**
- **T** requires: 2 units of V, 2 units of W, 2 units of X
- **U** requires: 2 units of Y, 3 units of Z
- **Lead times for components:**
- V: 2 weeks
- W: 3 weeks
- X: 1 week
- Y: 2 weeks
- Z: 1 week
---
### Step 2: Determine the gross requirements for S
| Week | Gross Req for S | On Hand | Net Req | Order Receipt | Order Release |
|--------|------------------|-----------|-----------|----------------|---------------|
| 4 | 150 | 0 | ? | ? | ? |
Since the demand for S is 150 units in week 7, and S takes 2 weeks to produce, the **production order for S** needs to be released **2 weeks before week 7**, i.e., in week 5.
---
### Step 3: Calculate net requirements for S
- **Week 7:**
- Gross requirement: 150 units
- On hand inventory at start of week 7: 0
- **Net requirement:** 150 units (since no inventory)
- **Order to be released:** 150 units in week 5
---
### Step 4: Calculate requirements for components T and U
Since each S needs 1 T and 1 U per unit:
| Week | Gross Req T | Gross Req U | On Hand T | On Hand U |
|--------|--------------|--------------|-----------|-----------|
| 7 | 150 | 150 | ? | ? |
- **T** takes 1 week to produce, needed in week 7, so **order for T** should be released **1 week before week 7**, i.e., in week 6.
- **U** takes 2 weeks to produce, needed in week 7, so **order for U** should be released **2 weeks before week 7**, i.e., in week 5.
---
### Step 5: Calculate requirements for subcomponents V, W, X, Y, Z
**For T:**
- 1 unit of T requires:
- 2 V
- 2 W
- 2 X
**For U:**
- 1 unit of U requires:
- 2 Y
- 3 Z
---
### Step 6: Determine gross requirements for T and U
| Week | Req T | Req U |
|--------|---------|--------|
| 7 | 150 | 150 |
- **Order releases:**
- T: in week 6 (to meet week 7 demand, 1-week lead time)
- U: in week 5 (to meet week 7 demand, 2-week lead time)
---
### Step 7: Calculate gross requirements for subcomponents
**V, W, X (from T):**
- Each T: needs 2 V, 2 W, 2 X
- T demand in week 6: 150 units
| Component | Requirement per unit of T | Total requirement in week 6 |
|--------------|----------------------------|----------------------------|
| V | 2 | 150 * 2 = 300 |
| W | 2 | 300 |
| X | 2 | 300 |
**Y, Z (from U):**
- Each U: needs 2 Y and 3 Z
- U demand in week 5: 150 units
| Component | Requirement per unit of U | Total requirement in week 5 |
|--------------|----------------------------|------------------------------|
| Y | 2 | 150 * 2 = 300 |
| Z | 3 | 150 * 3 = 450 |
---
### Step 8: Create a time-phased plan for components, considering lead times
**Component lead times:**
| Component | Lead Time (weeks) | Order release week | Requirement week |
|--------------|-------------------|---------------------|------------------|
| V | 2 | week 4 | week 6 |
| W | 3 | week 3 | week 6 |
| X | 1 | week 6 | week 6 |
| Y | 2 | week 3 | week 5 |
| Z | 1 | week 6 | week 5 |
---
### Step 9: Calculate net requirements for components
Assuming no starting inventory (on hand = 0), net requirements equal gross requirements.
---
### **Final table of net requirements:**
| Item | Week 4 | Week 5 | Week 6 | Week 7 |
|-------|---------|--------|--------|--------|
| **S** | 0 | 0 | 0 | 150 |
| **T** | 0 | 0 | 150 | 0 |
| **U** | 0 | 150 | 0 | 0 |
| **V** | 0 | 0 | 300 | 0 |
| **W** | 0 | 0 | 300 | 0 |
| **X** | 0 | 0 | 300 | 0 |
| **Y** | 0 | 0 | 0 | 300 |
| **Z** | 0 | 0 | 0 | 450 |
---
### **Summary of order releases:**
| Item | Week to release order | Quantity |
|--------|-------------------------|----------|
| S | Week 5 | 150 units (to meet week 7 demand) |
| T | Week 6 | 150 units (to meet week 7 requirement) |
| U | Week 5 | 150 units (to meet week 7 requirement) |
| V | Week 4 | 300 units (from T in week 6) |
| W | Week 3 | 300 units (from T in week 6) |
| X | Week 6 | 300 units (from T in week 6) |
| Y | Week 3 | 300 units (from U in week 5) |
| Z | Week 6 | 450 units (from U in week 5) |
---
### **Final notes:**
- Orders are scheduled considering lead times.
- On-hand inventory is assumed to be zero initially.
- All net requirements are whole numbers.
---
### **Final answer:**
| Item | Week 4 | Week 5 | Week 6 | Week 7 |
|-------|---------|--------|--------|--------|
| **S** | 0 | 0 | 0 | 150 |
| **T** | 0 | 0 | 150 | 0 |
| **U** | 0 | 150 | 0 | 0 |
| **V** | 0 | 0 | 300 | 0 |
| **W** | 0 | 0 | 300 | 0 |
| **X** | 0 | 0 | 300 | 0 |
| **Y** | 0 | 0 | 0 | 300 |
| **Z** | 0 | 0 | 0 | 450 |
This completes the step-by-step construction of the material requirements plan.