VIPSolutions logo ✨ VIPSolutions

Give step-by-step solution with explanation and final answer:3. A construction project has indirect (overhead) costs as $60 per day. Based on the details in the table below, calculate the optimum schedule and minimum total cost for the project. Duration Cost ($) Duration Cost ($) (days) (days) OEE ERNE Eo Taal EA

Question:

Give step-by-step solution with explanation and final answer:Uploaded Image3. A construction project has indirect (overhead) costs as $60 per day. Based on the details in the table below, calculate the optimum schedule and minimum total cost for the project. Duration Cost ($) Duration Cost ($) (days) (days) OEE ERNE Eo Taal EA

This is AI generated Response.
Asked by: VARRI APPARAO
Created at: 2025-10-19 07:32:17

Final Answer:

Rendered Raw Text
Did you like this answer?
Let's analyze the given data and solve the problem step-by-step. --- # Step 1: Understand the data | Activity | Predecessor(s) | Normal Duration | Normal Cost | Crash Duration | Crash Cost | |------------|----------------|-------------------|--------------|----------------|------------| | A | - | 2 days | \$120 | 2 days | - | | B | A | 5 days | \$180 | 4 days | \$240 | | C | B | 6 days | \$170 | 4 days | \$190 | | D | B | 7 days | \$150 | 5 days | \$185 | | E | C, D | 4 days | \$190 | 3 days | \$240 | --- # Step 2: Calculate the Normal and Crash Costs per day for each activity | Activity | Cost to Crash | Cost Difference | Duration Difference | Cost per Day to Crash | |------------|----------------|------------------|---------------------|------------------------| | B | \$240 - \$180 = \$60 | \$60 | 1 day | \$60 / 1 = \$60 | | C | \$190 - \$170 = \$20 | \$20 | 2 days | \$20 / 2 = \$10 | | D | \$185 - \$150 = \$35 | \$35 | 2 days | \$35 / 2 = \$17.5 | | E | \$240 - \$190 = \$50 | \$50 | 1 day | \$50 / 1 = \$50 | --- # Step 3: Find the critical path - The paths are: - Path 1: A → B → C → E - Path 2: A → B → D → E - **Critical Path (Longest Duration):** - Path 1: 2 + 5 + 6 + 4 = **17 days** - Path 2: 2 + 5 + 7 + 4 = **18 days** - The **critical path** is **A → B → D → E** with **18 days**. --- # Step 4: Determine the total normal cost Sum of normal costs: - A: \$120 - B: \$180 - D: \$150 - E: \$190 Total normal cost = \$120 + \$180 + \$150 + \$190 = **\$640** --- # Step 5: Determine the total crash cost for the critical path - For activities on the critical path, crash to their minimum durations: - A: already at 2 days (minimum) - B: from 5 to 4 days (cost \$60) - D: from 7 to 5 days (cost \$35) - E: from 4 to 3 days (cost \$50) - Additional costs to crash: - B: \$60 - D: \$35 - E: \$50 Total crash cost: - Normal cost: \$640 - Additional crash costs: \$60 + \$35 + \$50 = **\$145** Total crash cost = \$640 + \$145 = **\$785** --- # Step 6: Calculate the optimum schedule **Objective:** Minimize total cost while crashing activities on the critical path. - Crash activities with the lowest crash cost per day first: - D: \$17.5 per day (from 7 to 5 days) - C: \$10 per day (not on critical path) - E: \$50 per day (from 4 to 3 days) - B: \$60 per day (from 5 to 4 days) - Since the critical path is **A → B → D → E**, crash D, then E, then B, as cost per day: - Crash D from 7 to 5 days (cost \$35) - Crash E from 4 to 3 days (cost \$50) - Crash B from 5 to 4 days (cost \$60) Total days saved: - D: 2 days - E: 1 day - B: 1 day Total days reduced = 2 + 1 + 1 = 4 days Remaining critical path duration: - Total original duration: 18 days - After crashing: 18 - 4 = **14 days** --- # **Final answer:** - **Optimum Schedule Duration:** **14 days** - **Minimum Total Cost:** **\$785** --- # **Summary:** | Description | Value | |--------------|--------| | **Optimum duration** | **14 days** | | **Minimum total cost** | **\$785** | This schedule involves crashing activities B, D, and E to their minimum durations, reducing the project duration from 18 to 14 days at a total cost of \$785.

📢 Instructions:

  • Ask anything relatd to above question only.
  • For new Question goto :

Study Help, Fast Answers

VIPSolutions focuses on clear, step‑by‑step explanations so you can learn quickly. Whether you need an AI‑generated walkthrough or a short hint to get unstuck, each solution is organized for fast reading and easy review later.

Search similar questions, compare approaches, and bookmark the best answers for revision. Our goal is simple: quick, reliable study help that feels natural—not noisy.